Zoning Certificates/Building Permit Submissions
To ensure the Development Services Department is providing the most efficient customer service to the public, the following process has been implemented to ensure the required planning approvals are in place before submitting an Application for a Building Permit. Planning staff are the first contact for counter or phone inquiries, which ensures that projects can be reviewed for compliance with various planning documents prior to the submission of a “complete” building permit application. The purpose is to ensure that customer service is improved for contractors and residents in the Township, by providing them with guidance regarding the items they need to provide and meet with respect of the Township’s Zoning By-law, and any other planning related regulations and policies before commencing the building permit process.
An Application for Zoning Certificate will confirm that the proposed construction meets the regulations of the Township’s Zoning By-law or identify concerns with the proposed work. Planning staff will review the application to determine if the construction is exempt from the requirement of a Zoning Certificate or whether additional approvals are required from other department or agencies.
The following is the submission sequence:
Planning First/Zoning Certificate
- Apply for a Zoning Certificate on Cloudpermit, along with the required drawings in order to obtain a Zoning Certificate. The Planning Division will inform you of the requirements for approvals from Ministry of Transportation, County of Simcoe, or Conservation Authorities.
Complete Building Permit Submission
- Owner/Applicant to obtain all required permit approvals from the above authorities.
-
Apply for a building permit on Cloudpermit along with all required drawings, engineered lot grading details, an approved Zoning certificate, and all certificates and approvals from any outside authorities.
For additional questions, contact Planning or Building Division staff.
List of Exemptions from Zoning Certificate requirement (Building Permit may still be required)
- Foundation repairs
- Solid Fuel Burning Woodstoves and Fireplaces including chimney repairs
- Septic System Tank Replacement
- Repair to Retaining Wall
- Plumbing
- Electrical
- Back Flow Prevention Devices
- Roof Top Solar Panels
- Interior renovation unless related to Change of Use or Accessory Apartment
- Fire/Smoke Alarms
- Roof Repairs unless change in height
- Window Replacement
- Water Meter Installation
- Pergola
Contact Us
Township of Oro-Medonte Administration Centre
148 Line 7 South
Oro-Medonte, ON L0L 2E0
Phone: (705) 487-2171
Fax: (705) 487-0133
Sign up for our Council Highlights & Township Updates Newsletter
Stay up-to-date with Council meetings, important topics of discussion, and relevant information by subscribing to the Council Highlights & Township Updates eNewsletter!